• 0 Posts
  • 2 Comments
Joined 1 year ago
cake
Cake day: August 3rd, 2023

help-circle
  • I’m not super comfortable approving his work, but its functional and I don’t want to hold up sprints…

    I know it’s not the point of your post, but this is a red flag to me. If you’re using scrum (which it sounds like you are?), a sprint isn’t defined as “when all the stories get to done”, it’s a set block of time (generally between 2 and 4 weeks). If the stories don’t get to done in the time period, you don’t hold up the sprint - they just didn’t get to done. Most teams will just refactor the story into smaller pieces to carry over to following sprints.